MMH Hurricane Tie
Product Details
The versatile MMH8 line of connectors provides uplift resistance for roof trusses and rafters for factory-built structures. The nailing grids in the MMH8 replace traditional nail holes allowing for faster installation of power-driven nails. The MMH8 nailing grids also permit multiple nailing pattern options to enable value engineering for different load levels. Connectors have been evaluated with and without 5/8" bearing strips.
Material
- 18 gauge
Finish
- Galvanized
Installation
- Use all specified fasteners; see General Notes.
- Hurricane ties do not replace solid blocking.
- When installing ties on plated trusses (on the side opposite the truss plate) do not fasten through the truss plate from behind. This can force the truss plate off of the truss and compromise truss performance.
- MMH8 nails must be installed with a power nailer. Full face and eye protection is required. Extreme caution is required when driving nails through the MMH8. To prevent ricochet, drive nails straight through the nailing grid. Follow all safety instructions for the nail tool. Adjust the nail drive by setting the depth-of-drive on the nailer tool so that nail heads are driven into contact with the hanger. Do not over-drive nails, which are indicated by the tops of the nail heads driven below the top surface of the metal connector.
- MMH8 nails must have a minimum 1/2" center-to-center spacing in the same nailing grid and not split the wood. The square nailing grid must contain a minimum of three nails, and a maximum of five nails. In order for the 1/2" spacing requirement to be met with five nails in the square nailing grid, nails shall be positioned at the four corners of the grid, with the fifth nail positioned in the center of the grid.
Related Literature
Load Tables
SPF/HF Roof Uplift Connector Installation and Allowable Load Table
Model No. | Fasteners (in.) | DF/SP/SPF/HF Allowable Loads (lb.) | |||||||
---|---|---|---|---|---|---|---|---|---|
To Rafter | To Plates | To Studs | No Bearing Strip | 5/8" Bearing Strip | |||||
Uplift (160) | Lateral (160) | Uplift (160) | Lateral (160) | ||||||
F1 | F2 | F1 | F2 | ||||||
MMH8 | (3) 0.131 x 1 1/2 | (3) 0.131 x 1 1/2 | — | 170 | — | — | 170 | — | — |
(5) 0.131 x 1 1/2 | (5) 0.131 x 1 1/2 | — | 285 | 55 | — | 285 | 55 | — | |
(6) 0.131 x 1 1/2 | (6) 0.131 x 1 1/2 | — | 410 | 65 | — | 410 | 65 | — |
- Loads have been increased for wind or earthquake loading with no further increase allowed; reduce where other loads govern.
- Allowable loads are for one connector. A minimum rafter thickness of 2 1/2" must be used when connectors are used on each side of the rafter and on the same side of the plate (exception: connectors installed such that fasteners on opposite side do not interfere).
- Allowable loads in the F1 direction are not intended to replace diaphragm boundary members and do not account for possible cross-grain bending of the truss or rafter members.
- When cross-grain bending or cross-grain tension cannot be avoided in the members, mechanical reinforcement to resist such forces shall be considered by the designer.
- Connector installation on the outside of the wall is acceptable, provided a minimum 3 1/2" overhang. For a Continuous Uplift Load Path, connections in the same area (i.e., truss-to-plate connector and plate-to-stud connector) must be on the same side of the wall.
- Fasteners: Nail dimensions are listed diameter by length. 0.148" x 1 1/2" nails may be substituted for nails shown at table loads.